Boiler Sediment Buildup Removal Procedure
Materials: Scale Kleen, Tub for soaking boiler, rubber gloves, tools, 5 gallons of hot water, baking soda.
Remove boiler from machine
Tip: Before you begin, take reference pictures for reassembly
Remove fittings, elements, and gaskets from boiler
Create Scale Kleen bath (2.2lbs to 5 gallons) Use Scale Kleen instructions on the bottle. https://www.amazon.com/Everpure-EV9798-35-Scalekleen-Scale-Remover/dp/B005INBJKY
Submerge Boiler
If larger than bucket, submerge half boiler at a time
Leave submerged for 1-12 hours depending on severity
Remove boiler – wearing rubber gloves
Rinse boiler thoroughly
Inspect for approval (scale sufficiently removed) Rinse any extra sediment out.
If scale is sufficiently removed, move on to step 9
If scale is still present, return to step 4.
Scale Kleen is drain safe, discard in normal waste drain.
Create baking soda neutralizing bath
8oz package of Baking soda to 5 gallons of water. Mix thoroughly.
Submerge in baking soda bath for 5 minutes
Rinse boiler thoroughly
Inspect for cleanliness – no scale bits inside boiler, no baking soda inside boiler.
Re-attach fittings
Use pictures as guide
Re-install boiler
Test machine – verify for leaks, operation.
Related Articles
Long Backflush Procedure - Universal
Long Backflush - Unclogging Brew Solenoid SLAYER Espresso Machines feature 24vDC 3-Way Solenoid Valves on each group head. The valves are located off the rear of the group neck and are the main gateway for water flowing through the brew circuit. ...
Single Group Display Removal and Replacement
Single Group Display Removal and Replacement Time Needed: 15 Min Parts Needed: Single Group Screen Tools Needed: #2 Screwdriver, 5/64 Allen Step 1: Turn off machine and unplug Step 2: Remove cup tray Step 3: Remove back panel, two screws under where ...
Hard Reset Procedure Steam EP
Hard Reset Procedure Steam EP Turn off breaker switch, and main power Hold the water button and the toggle button at the same time Have someone switch on main power, hold until you read "Preset Done" Turn off the main power, wait 10 seconds, turn on ...
Checking Operations of Pre-Heat Boiler, V3
Checking Operations of Pre-Heat Boiler V3 Tools needed: Multi Meter, Screwdriver Time Needed: 30 minutes Check your love controller, press set once and it'll illuminate a red dot under out1. Is the setting correct? Please verify all settings for the ...
Slayer Steam Panel Removal and Installation
Slayer Steam Panel Removal and Installation Tools Needed: crescent wrench, #2 screwdriver, #4 allen key Time: 30-45 minutes Turn off water and power, unplug the machine Remove the top cup tray Remove panel screws while supporting the panel. Set ...