Checking Operations of Pre-Heat Boiler, V3

Checking Operations of Pre-Heat Boiler, V3

Checking Operations of Pre-Heat Boiler V3

Tools needed: Multi Meter, Screwdriver

Time Needed: 30 minutes

Check your love controller, press set once and it'll illuminate a red dot under out1. Is the setting correct? Please verify all settings for the preheat. Typically set to 185f or equivalent


Remove cup tray

Remove side panel


Remove covering of element leads


With you meter set to read AC voltage remove the long wire from the limit thermostat and check voltage at the element. One lead on the element and one lead to ground


Check voltage with one lead to the long wire (typically brown) and one lead to ground


You will only receive voltage on the long wire if the love controller is calling for heat. That is indicated by a red dot under OUT1


Disconnect wires from limit thermostat and check continuity


Continuity is checked with the meter set to the symbol that looks like "wifi"


Depending on the meter, you'll hear a tone or get a reading on the front of the meter if continuity is present


Check resistance of your element. Switch your meter to read resistance symbolized by the omega symbol Ω One lead of multi meter on each element leads. 




    • Related Articles

    • Pre-Infusion Solenoid Troubleshooting - Steam LP

      Pre-Infusion Solenoid Troubleshooting - Steam LP Slayer recommends that all service be performed by an experienced Slayer Espresso trained technician. Slayer Steam LP's Pre-Infusion solenoid is a 24v DC 3-way solenoid which enables a group to ...
    • Pre-Brew Calibration - Espresso Series

      Pre-Brew Flow Rate Calibration - Slayer V3 & Single Group Slayer Espresso Series machines feature a precision Needle Valve which controls the flow rate of water during the Pre-Brew phase of an extraction. This flow rate control allows the barista to ...
    • Replace Pre-Infusion Solenoid Slayer Steam LP

      Replace Pre-Infusion Solenoid Slayer Steam LP Time Needed: :30min - 1:00hr Tools Needed: Adjustable wrench, #2 screw driver.  Turn off the machine, unplug from power source.  Turn off water.  Raise hood of the machine Open Drain Line for group being ...
    • Resistance Specifications - Universal

      Resistance Specifications Espresso V3, Single Group, & Steam Series SLAYER recommends that all service be performed by an experienced SLAYER Espresso trained technician. Temperature Probe Resistance Espresso V3 Thermocouple Resistance Room Temp: ...
    • Boiler Sediment Removal Procedure

      Boiler Sediment Buildup Removal Procedure Materials: Scale Kleen, Tub for soaking boiler, rubber gloves, tools, 5 gallons of hot water, baking soda. Remove boiler from machine Tip: Before you begin, take reference pictures for reassembly Remove ...