Slayer Steam Panel Removal and Installation

Slayer Steam Panel Removal and Installation

Slayer Steam Panel Removal and Installation


Tools Needed: crescent wrench, #2 screwdriver, #4 allen key
Time: 30-45 minutes


Turn off water and power, unplug the machine

Remove the top cup tray

Remove panel screws while supporting the panel. Set panels aside. 




While supporting the panel remove the lower front panel screws. For Steam X and LP Lower cup tray to its lowest position, disconnect the shot light and manual button when applicable





Remove the cup tray adjustment pin. With the crescent wrench loosen the lock nut, Unscrew the pin. 





While supporting the hook panel, use the #4 allen remove the internal bolt holding the hook on. 



Remove the panel

Reassemble in the same fashion. 
    • Related Articles

    • Panel Installation - Single Group

      Single Group Panel Installation Slayer recommends that all service be performed by an experienced Slayer Espresso trained technician. Objective: Install and remove panels for maintenance, service, and panel replacement. Please contact Slayer Tech ...
    • Slayer Espresso Installation Cut Sheets 2023

      Installation Cut Sheets for Slayer Espresso and Steam Series Slayer recommends that all service be performed by an experienced Slayer Espresso trained technician. Questions or concerns? Please contact: support@slayerespresso.com
    • Program and Calibrate Volumetrics - Slayer Steam X

      Program and Calibrate Slayer Steam X Volumetrics Time: 10 minutes Tools: Espresso Scale Preparation: Calibrating volumetrics requires considerate espresso preparation. External factors such as coffee, dose, and tamp equally contribute to the quality ...
    • Panel Alignment - Single Group

      Slayer Single Group Panel Alignment - 2023 Model Slayer recommends that all service be performed by an experienced Slayer Espresso trained technician. Purpose: Re-align side panels to base plate. Commonly caused by rough transit or loose bolts. ...
    • Removing Upper Front Panel - Steam Series

      Raising The Hood Objective: Remove upper front panel in order to perform service. Time: 30 minutes Tools: #2 Philips Head Screw Driver 1/2" Wrench Step 1: Turn off machine and unplug from power. Shut off water feed. Step 2: Remove the cup tray panels ...